Murray Basin Rail Project caught in budget impasse

THE $440 million Murray Rail Basin Project is stuck in no man’s land after the political blame game over who is responsible for funding it sank to a new low on Thursday.

The Andrews Government kicked in $48.8 million for the half-completed, nation-building project – which would fix a century-old rail network – in this week’s State Budget.

But it fell well short of the $244 million needed to complete it, with the government saying it would seek an additional $195.2 million from the Commonwealth to get the work done.

It prompted Deputy Prime Minister Michael McCormack to weigh into the issue on Thursday.

He told Sunraysia Daily the Victorian Government was “entirely responsible for works” on the much-needed rail project, which would take tens of thousands of trucks off the roads during harvest season.

“It is important to remember that the Murray Basin Freight Rail network is a Victorian Government-owned and operated asset,” Mr McCormack said.

“Nonetheless, the Australian Government is considering next steps to address the significant challenges faced by industry and communities as a result of the project being halted by the Victorian Government.”

The five-stage project – which stalled in June last year – would standardise hundreds of kilometres of tracks, from the Manangatang line to the Port of Melbourne, bringing freight services into the 21st century and possibly paving the way for passenger rail services to Mildura.

The State Government sent a revised business case for the project to the Federal Government in May. However, it fails to standardise rail to Sea Lake and Manangatang.

The latest plan remains in the corridors of the Federal Department of Transport, Regional Development and Communications — Mr McCormack’s department.

“We are very disappointed that the Federal Government once again let Victoria down by refusing to fund anything for this project (in the Federal Budget in October),” Victorian Agriculture Minister Jaclyn Symes said.

Victorian Transport Infrastructure Minister Jacinta Allan added: “The original business case was significantly deficient in a number of ways.

“That original scope massively underestimated the cost,” Ms Allan said.

As grain growers are left fuming over the impasse, Member for Mildura Ali Cupper called on the state and federal governments to stop the blame game.

“I have maintained all along that the Murray Basin Rail Project should be completed in full, and ultimately who funds it is largely irrelevant,” the independent MP said on Thursday.

“I am continuing to press the Victorian Government about the standardisation of the Sea Lake and Manangatang lines being left out of the revised business case.

“The Federal Government is not powerless in all of this though. They have an opportunity to ensure the project is funded in full, if they choose.”

Federal Member for Mallee Anne Webster said the failure of the Victorian Government to allocate funding for the completion of the Murray Basin Rail Project was “beyond disappointing”.

“It is clear the Victorian Government has disregarded the concerns of stakeholders and the needs of regional Victoria by refusing to accept their responsibility to complete this project,” Dr Webster said.

Digital Editions


  • Easter festivities start tomorrow

    Easter festivities start tomorrow

    Gannawarra will be gearing up with activities, events and excitement this long weekend, from the roar of modified machinery in Quambatook to face‑painting and a…

More News

  • It’s time to detox

    It’s time to detox

    RESIDENTS needing to rid their home of unused household chemicals will be able to do so for free. Sustainability Victoria is bringing its Detox Your Home service to the Kerang…

  • Lions roar to first win

    Lions roar to first win

    HAY claimed its first Central Murray A grade victory, overcoming Tyntynder in a physical opening round clash by 15 goals on Saturday. Despite both sides taking to the court missing…

  • Swans start season strong

    Swans start season strong

    A 15-GOAL to eight second quarter helped Swan Hill secure their first points under new coach Milly McDonald, with the Swans recording a 25-goal win over Ultima on Saturday. The…

  • Celebrating Easter

    Celebrating Easter

    Anglican Kerang Friday, 3 April 3 – Good Friday, 9.30am Stations of the Cross with Kerang Combined Churches. Atkinson Park. Sunday, 5 April – Easter Sunday, 10am Holy Communion with…

  • Golf Notes

    Golf Notes

    KERANG Ladies Par – Wednesday, March 25 TEN women fronted up to play a par competition on Wednesday morning, with a very thick fog that disappeared just before hit off.…

  • Bowls Notes

    Bowls Notes

    KERANG TWENTY four players enjoyed Black Duck Jackpot triples last week. The jackpot number was +12 and, unfortunately, our team finished on -12, prompting another round of ‘if only.’ Never…

  • Swans spoil Storm party

    Swans spoil Storm party

    AT the start of the season, new Swan Hill coach, Jason Murphy wanted his side to “become hated again” just like the Swans of old back in the 20th century.…

  • Gearing up for Easter

    Gearing up for Easter

    GANNAWARRA will be teeming with activities, events and excitement this long weekend, from the roar of modified machinery in Quambatook to face-painting and a visit from the Easter Bunny in…

  • Lions make statement

    Lions make statement

    HAY has broken through for a landmark first victory in the Central Murray, defeating Tyntynder by 52 points in an emphatic performance at the Alan Garden Reserve on Saturday. In…

  • Wettest March in 80 years

    Wettest March in 80 years

    KERANG has been drenched, recording its wettest March in nearly 80 years. The district received a total of 121.8mm of rain across nine days this month, with a massive 83.8mm…